Royal Bolton Hospital

Following our successful refurbishment of Christies Hospital AHU we were gratefully recommended to Royal Bolton Hospital
Efficient Cool Heat were asked to completely overhaul the existing AHU ‘s whilst in situ. These also had been installed 27 years previously.

Bringing it up to date with the latest energy efficient technology and Increasing longevity for up to 25 years. Replacing the AHU’s was not a option as the plant room had been built around them.

We completely stripped the internal units removing all previous:

  • Dampers
  • Frost Coils
  • Filter Banks
  • Heating Coils
  • DX Coils
  • Motors
  • Scrolls

We then completely sanded and treated the inner housing with specialised oxide anti corrosive paint. A specialist heavy duty paint was then applied as a top coat.

We then installed:

  • New Dampers
  • Pre filters
  • Bare Tube Frost Coils
  • Filters
  • Bag Filters
  • Steam Coils
  • LPHW coils
  • DX cooling coils
  • Inverter Drive fan scrolls

Blygold Treated for the coils which prevents corrosion and enhances longevity.

royal-bolton-hospital-logo